News

JMT’s accelerated bridge construction (ABC) techniques on the I-78 under clearance project in Berks County, PA recently received a Transportation Special Solution Award during the Precast/Prestressed Concrete Institute (PCI) 2020 Design Awards. This project was the first of its kind in Pennsylvania.

The PCI Design Awards recognizes “design excellence and construction quality using precast concrete,” according to the organization. PCI “is the technical institute and trade association for the precast/prestressed concrete structures industry.”

The Pennsylvania Department of Transportation (PennDOT) sought to replace six bridges over I-78 to increase the minimum vertical clearance and accommodate future widening. Alfred Benesch & Company and JMT were independently selected by PennDOT to design two separate packages, each consisting of three structures along this corridor between Harrisburg and Allentown. Initially, these bridges were to be constructed using conventional techniques under staged construction, maintaining a single lane of traffic in each direction. During the design process, PennDOT asked the teams to merge their efforts and produce a single bid package that incorporated ABC techniques under roadway closures to accelerate the project. In addition, some economy of scale was anticipated considering the similarities of the six structures.

This was PennDOT’s first project featuring tall abutments to be constructed using precast elements specifically designed for this purpose. The six-bridge package allowed the contractor and pre-caster to become efficient with this technique.  JMT was the lead project manager during the design process, which included both the innovative bridge design and an equally innovative procurement method to allow for the valuing of road users’ time as part of the low bid calculation.

All existing structures were three-span bridges with short end spans comprised of spread box beams and a longer center span over I-78 consisting of adjacent box beams. The existing piers were multicolumn bents supported on spread footings, while the abutments were stub abutments supported on piles. All six replacement bridges were single-span composite, prestressed concrete bulb-tee beam bridges with stained architectural surface treatments. The abutments were typically tall cantilever abutments supported on spread footings. ABC components utilized on the project included prefabricated bridge elements (footings, stems, pedestals, post-tensioned deck panels, approach slabs, sleeper slabs, and moment slabs) and the use of ultra high-performance concrete and grouted splice couplers.

The use of ABC greatly shortened the on-site construction duration for each of the six structures. Each of the six structures would have taken a full construction season to complete. By implementing ABC under roadway closures, the on-site construction time for each of the six bridges was reduced to less than 45 calendar days. The project met the owner’s needs of providing standard interstate under clearance and allowing for the future reconstruction of I-78 while maintaining four lanes of traffic on either side and designing an aesthetically pleasing group of structures.

Back to All News